Waterline Work for H-1 Eastbound Improvements Between Ola Lane Overpass and Likelike Highway
Work On a Waterline Connection Under the H-1 Eastbound will Require Two-Lane Closures Between the Middle Street Merge and the Likelike Highway Off-Ramp Over Two Weekends
HONOLULU – The Hawai‘i Department of Transportation (HDOT) notifies drivers of planned continuous weekend closures on the Interstate H-1 Freeway in the eastbound direction between the Middle Street merge and the Likelike Highway off-ramp. The closure is scheduled to begin at 9 p.m. Friday, Feb. 13 and will continue until 4:30 a.m. Monday, Feb. 16, 2026. Weekend closures for Feb. 20-23, Feb. 27 – March 2 and March 6-9 have been set as contingency dates in the event of weather or construction delays.
Associated closures will include:
- Single right-lane closure on H-1 eastbound between the Ola Lane Overpass and the Middle Street merge, to provide a safe taper at freeway speeds for the work zone.
- Closure of the King Street on-ramp to the H-1 eastbound.
- Single right-lane closure on the H-1 Airport Viaduct eastbound as it approaches the merge.
- The closure of the two right lanes of the H-1 eastbound between the Middle Street merge and the Likelike Highway off-ramp.
The closure is needed to tie in the new 36-inch waterline being constructed as part of the Interstate Route H-1 Eastbound Improvements, Ola Lane Overpass to Likelike Highway off-ramp. Homes and businesses serviced by this waterline are currently being served by bypass lines and will not experience a loss in service during the tie in.
Special duty police officers will be on-site to assist with traffic control and safety procedures. Electronic message boards will be posted to notify motorists of closure information.
The Interstate Route H-1 Eastbound Improvements, Ola Lane Overpass to Likelike Highway off-ramp is designed to improve safety and efficiency on the interstate by eliminating a merge and adding emergency shoulders. The Gulick Avenue Overpass, currently the lowest vertical clearance on O‘ahu, will be rehabilitated through the project and will gain approximately 6 inches in height.
The estimated completion date for the Eastbound H-1 Freeway Improvements Project is October 2027, weather permitting. For more information, please view the project website at https://h1widening.com/
For a full list of lane closures scheduled on state roadways, please visit the HDOT website at https://hidot.hawaii.gov/highways/roadwork/.
###
Legal Disclaimer:
EIN Presswire provides this news content "as is" without warranty of any kind. We do not accept any responsibility or liability for the accuracy, content, images, videos, licenses, completeness, legality, or reliability of the information contained in this article. If you have any complaints or copyright issues related to this article, kindly contact the author above.